Project Description
Owner:
MoTI
Design Engineer / Consultant:
Associated Engineering
Contract Value:
$20M
Scheduled Duration:
2019 – 2020
Project Description:
The Highway 7 – Haney Bypass Intersection Improvements project in Maple Ridge was a large infrastructure improvement project that required insignificant coordination between multiple stakeholders. The objective of the project was to improve traffic along the Highway 7 corridor. The significant upgrades included reconfiguration of the intersection of Highway 7 and 222nd, reconfiguration of the intersection of Highway 7 and Kanaka Way, reconfiguration of the intersection of Haney Bypass and 225th Street, signalization at Callaghan Road.